Expansion or movement joints are an important part of any brick slip installation and are required with all Eurobrick systems. They allow for the natural movement of different materials and help protect the integrity and long-term performance of the cladding.
We are sometimes asked where movement joints are needed, why they are necessary and how they should be constructed. Here, we take a closer look at their role within a brick slip system.
Why are movement joints necessary?
All buildings and construction materials are subject to some degree of movement. This may be caused by thermal expansion and contraction, structural movement, settlement or, in timber frame construction, shrinkage of the frame.
Brick slips also absorb radiant energy from the sun. As they have considerably less mass than a full-thickness brick, they can heat up and cool down differently from traditional masonry. Importantly, their rate of expansion and contraction may also differ from that of the backer panels to which they are attached.
Movement joints help accommodate this differential movement and prevent damaging stresses from building up within the cladding system. Without suitable provision for movement, problems can develop over time, potentially including delamination of backer panels or detachment of brick slips.
We have supplied projects where Eurobrick systems have been installed to replace other brick slip systems that have failed over time, with inadequate provision for movement being a significant contributing factor.

Where are movement joints required?
For Eurobrick systems, movement joints are required at intervals not exceeding 6m, measured vertically or horizontally across uninterrupted brick slip cladding.
There are also particular areas where provision for movement should be considered, including:
- Abutments with other materials – such as where brick slip cladding meets traditional masonry or another type of cladding.
- Adjoining elevations – where different levels of thermal movement may be anticipated due to the orientation of the building and exposure to the sun.
- Timber frame construction – where shrinkage and settlement of the frame must be accommodated. Joints may be required at every floor level depending on the construction and anticipated movement.
- Existing structural movement joints – which should always be carried through the brick slip cladding system.
- Transitions between different forms of construction – particularly where brick slip cladding is supported by the building frame but adjoining traditional masonry is ground bearing.
This list is not exhaustive, so we always recommend seeking technical advice where there is any uncertainty about the requirements of a particular project.
For timber frame projects, the extent of anticipated shrinkage can depend on several factors, including whether the roof, dry lining or floor materials have already been installed. The project engineer or timber frame supplier should be able to provide project-specific guidance.
How should movement joints be constructed?
Movement joints should comprise a complete break through both the brick slips and the Eurobrick system backer panel, typically approximately 15mm wide.
Eurobrick supplies a 20mm thick compressible polyethylene joint filler rod, which can be used to take up most of the depth of the joint. This can then be finished with polysulphide mastic or a similar suitable non-aggressive sealant.
System panels should be fully fixed in accordance with the relevant Eurobrick Installation Instructions, with lines of fixings positioned on both sides of the movement joint.

Minimising the visual impact
Although the maximum recommended spans between movement joints should never be exceeded, there is often some flexibility in their positioning. Careful planning at the design stage can help reduce their visual impact on an elevation.
For example, vertical or horizontal joints can intersect with or spring from window and door openings, reducing the overall length of the joint. Where practical, joints can also be positioned behind rainwater downpipes.
Considering movement joints early in the design process can help ensure that both the technical and aesthetic requirements of the project are addressed.
Correct provision for movement is essential to the long-term performance of a brick slip installation. Every project is different, so movement joint requirements should always be considered alongside the building structure, substrate, materials and relevant installation guidance.
Our technical team is available to advise on Eurobrick systems and help with project-specific queries, including the positioning and construction of movement joints.